Acquisition Process

THE PROCEDURE OF ENTITLEMENTS AND COMPENSATION SCDP

The Procedure of Entitlements and Compensation SCDP

Land Acquisition has done under the Land Acquisition Act No 9 of 1950.

The Statutory Valuation of the property (land & buildings) are to be decided by the Chief Valuer – Government Valuation Department and having done so they have informed such valuations to the Affected Persons (APs) as per the Section 17 of the Land Acquisition Act.

All Affected Persons have been summoned to the LARC Committees.

If the Affected Persons are not satisfied with the LARC decision, they can appeal to the Super LARC Committee.

If the Affected Persons are not satisfied with the LARC decision, They can again appeal to the Government Compensation Review Board.

If they are not satisfied with the decision of Compensation Review Board, the APs have the right to go to the Court of Law and file a case under the Civil Law.

Accelerated Land Acquisition Process

Time period (72 Weeks)


1. Conduct Land Investigation - 02 Weeks
2. Calling Tender for Tracing - 04 Weeks
3. Preparation draft Tracing - 04 Weeks
4. Estimation of land by Valuation Department - 02 Weeks
5. Application - 02 Weeks
6. Section 2 - 04 Weeks
7. Preparation of Advance Tracing - 06 Weeks
8. Section 38 A - 04 Weeks
9. Condition report - 04 Weeks
10. Section 5 Gazztting - 04 Weeks
11. Section 6 (Preparation PP) - 04 Weeks
12. Section 7 Gazztting - 04 Weeks
13. Section 9 (Ownership inquiries ) - 08 Weeks
14. Section 10.1 - 04 Weeks
15. Valuation Report - 06 Weeks
16. Section 17 - 04 Weeks
17. LARC Meeting - 04 Weeks
18. Compensation payment - 02 Weeks